Wednesday, August 12, 2009

Week 5 August 12, 2009




The cement slab that was taken out of the living room basement makes a great "stoop" outside the doorway. Hopefully it will help prevent a big mud hole there. They also removed the pole that was holding up the house and the house didn't fall! In the one corner of the floor we are not having cement poured. They put in some framing to keep it open. This will allow for easier possibility to put a bathroom in the basement in the future. The hole in the gravel is to allow for thicker cement there for a pole that will support a beam. They plan to be here at the crack of dawn tomorrow to pour the floor in this area. The weather forecast is not too favorable for late tomorrow and Friday but they think they can get this room poured and cured enough before the rain comes in. The other area probably won't get poured until Monday or Tuesday, depending on when the weather clears.