We got two doors in today, the door to the basement under the kitchen and the east door of the living room.

The windows for the dormer also came in...

And a tub/shower...

The plumber and electrician were busy this week. Pipes and wires everywhere! Unfortunately some of it will need to be redone, like the thermostat for the kitchen heater is placed right in the middle of the only wall in the kitchen! Why didn't they put it at the edge!? And they put in the bathroom plumbing for a 3 ft vanity when we got a 4 ft vanity! They'll need to move the toilet closer to the shower.

Most of the lights are the recessed can lights- lots of light for not a lot of money!